Ellendale ND mining rig deployment
Company: Marathon Digital - Project: Ellendale
The claim, verbatim
57,000 S19 XP mining units expected to be deployed at Ellendale, ND during first half of 2023 with energization beginning late first quarter 2023
Source (primary)
Marathon Digital 10-K filed 2023-03-16 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗
Quote: “Approximately 57,000 S19 XPs are expected to be deployed at this site during the first half of 2023. Energization is expected to start late in the first quarter of 2023”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms Marathon Digital 10-K filed 2023-03-16
Quote: “Approximately 57,000 S19 XPs are expected to be deployed at this site during the first half of 2023. Energization is expected to start late in the first quarter of 2023”