For Oklo’s Meta-Backed 1.2 GW Campus, the First Firm Date Is 2029 Fuel, Not a Reactor

Uranium enrichment centrifuge hall in Ohio supplying HALEU fuel for Oklo nuclear reactors backed by Meta

TL;DR · 30-second read

The Short Version

Meta, the company behind Facebook and Instagram, is paying in advance for electricity from new nuclear power plants that have not been built yet, as tech companies hunt for enough power to run artificial intelligence. Some of that money is already paying for the plants’ fuel.

The nuclear startup Oklo has now locked in enough special uranium fuel for up to five of its reactors, delivered from a plant in Ohio starting in 2029. Its planned Ohio site would make roughly as much power as one large traditional nuclear plant.

The surprise: the fuel now has a delivery date. The reactors still do not.

On November 12, 2026, Oklo announced multiple definitive, multi-year contracts to buy high-assay low-enriched uranium (HALEU) from Centrus Energy, formalizing a letter of intent the two signed in June. The contracts cover enough fuel for up to five of Oklo’s Aurora powerhouses for multiple years, with deliveries from Centrus’ American Centrifuge Plant in Pike County, Ohio, scheduled to begin in 2029. The purchase is supported by Meta’s prepayment for future Oklo power and secures fuel for the first phase of Oklo’s planned 1.2-gigawatt power campus in Ohio. Centrus filed the announcement as an exhibit to an 8-K the same day. The companies described “meaningful prepayments and advances” but disclosed no dollar figure.

TIKR.com reported that Oklo’s third-quarter filing shows Meta’s first funding installment was released from escrow on November 2 and paid directly to Centrus as a credit toward fuel orders; that Meta signed its prepayment agreement with Oklo in January; that Oklo raised about $2.3 billion through stock sales in the first nine months of 2026 and announced a further $1 billion at-the-market offering program in September; and that Piper Sandler raised its estimated construction cost for new Oklo plants to $7,000 per kilowatt from $4,000.

Executive Summary

Oklo has turned a June letter of intent into binding fuel contracts with Centrus Energy, the only US-listed company building new domestic uranium enrichment at Piketon, Ohio. The fuel is HALEU, uranium enriched above the level used in most of today’s reactors, which designs like Oklo’s Aurora require. The contracts cover up to five powerhouses for multiple years, the first phase of Oklo’s 1.2 GW Ohio campus, future Aurora projects and later refueling of Oklo’s first reactor in Idaho.

The structure matters as much as the volume. Meta prepays Oklo for electricity it will buy later. Oklo uses that support to prepay Centrus for fuel. Centrus uses those prepayments, in its CEO Amir Vexler’s words, to “help fund our build out” of centrifuge capacity. Money from one of the largest buyers of data center power is now flowing two steps upstream, into the enrichment plant itself.

The result is an unusual sequencing. For the Ohio campus, the one hard, dated commitment either company has published is fuel delivery in 2029. No reactor in-service date, construction start, construction budget, power price or Ohio license accompanies it. Fuel is the furthest-advanced piece of the project, and the rest of the schedule now has to catch up to it.

The Only Date on the Ohio Campus Is a Fuel Date

The joint Oklo–Centrus announcement attached to Centrus’ November 12 8-K is specific about fuel: definitive contracts, multi-year terms, enough HALEU for up to five Aurora powerhouses, and deliveries from Piketon beginning in 2029. It is not specific about reactors. It describes the 1.2 GW campus as “planned” and gives no date for when the first Ohio unit starts construction, receives a Nuclear Regulatory Commission license or delivers electricity. Oklo’s own description of its regulatory progress refers to a combined license application (the single permit the NRC can grant to both build and operate a plant) submitted for an advanced reactor, not to approvals for Ohio.

That ordering follows from lead times. Oklo’s first reactor in Idaho runs on recovered fuel from Idaho National Laboratory’s decommissioned Experimental Breeder Reactor II. That is a one-off stockpile, not a supply chain. Every reactor after it depends on newly enriched HALEU, and the commercial capacity to make it in the US is still being built. Centrus says it has only recently completed and begun shipping its first new centrifuge. A developer that waited for reactor licenses before ordering fuel would risk finding that enrichment capacity had been committed elsewhere or never financed. Signing fuel first, with a customer’s money behind it, is how Oklo secures a place in a queue that does not exist yet at scale.

The practical consequence is for whoever buys power from advanced nuclear. A 2029 fuel date sets a floor, not a target. The Ohio units cannot run on Centrus fuel before it arrives, and the dates that decide when Meta’s data centers actually draw nuclear electricity (licensing, construction, commissioning) remain undisclosed. Power buyers comparing advanced-nuclear offers can now ask a sharper question: does the developer have dated, paid-for fuel, or only a reactor design and an application?

AI Buyer Money Is Moving Two Steps Upstream

Prepayment, meaning a buyer paying today for output delivered later, is a familiar tool when a supplier needs capital to build capacity. What is new here is the chain. Meta’s prepayment for future Oklo power, signed in January, is now tied to fuel procurement. Meta’s earlier agreement with Oklo, the release notes, “linked prepayment for power with advancement of project development,” and fuel is the first development milestone that agreement has visibly funded.

For Centrus, the effect is direct. Vexler said Oklo’s prepayments “add to the others we have previously received,” and the company says it now holds $5.4 billion in customer contracts and commitments to buy low-enriched uranium and HALEU from its new capacity. Customer money arriving before production reduces how much Centrus must raise elsewhere to expand Piketon. The same day the fuel deal was announced, Meta’s own 8-K recorded the completion of a €9 billion senior-note offering across six maturities from 2031 to 2065. That filing does not connect the debt to Oklo. It does show the scale of capital the largest data center operators, often called hyperscalers, now raise, and why a fuel prepayment is a small enough line item for one of them to absorb on a supplier’s behalf.

What a Fuel Contract Does Not De-Risk

Securing fuel removes one uncertainty and leaves the larger ones intact. TIKR reported Piper Sandler’s construction-cost estimate for new Oklo plants rising from $4,000 to $7,000 per kilowatt. At that level, the cost of building the reactors, not buying their fuel, dominates the project’s economics. Oklo has financed itself largely by issuing shares: about $2.3 billion in 2026 so far, plus a $1 billion at-the-market program, in which new shares are sold gradually into the market. Prepaid fuel lowers one funding need. It does not answer how the plants themselves are paid for.

Centrus carries its own execution risk, which its filings spell out. Its forward-looking statements cite dependence on appropriated federal HALEU funding, its lease of the Piketon facility, uncertainty over whether HALEU demand materializes at expected levels, competition from foreign enrichers, and its ability to execute expansions in Piketon and Oak Ridge, Tennessee. The 2029 delivery date depends on that buildout staying on schedule. Fuel arriving in 2029 for reactors that slip would also raise a question neither company has addressed: what happens to prepaid fuel that has no reactor ready to receive it.

Background

Oklo is a US developer of fast fission power plants, a class of advanced reactor that runs on higher-enriched fuel than conventional plants. It received the first Department of Energy site use permit for a commercial advanced fission plant, was awarded recovered fuel from Idaho National Laboratory for its first Aurora unit, and submitted the first custom combined license application for an advanced reactor to the Nuclear Regulatory Commission. In January 2026 it signed a prepayment agreement with Meta tied to future power from a planned 1.2 GW campus in Ohio, followed by a fuel letter of intent with Centrus in June.

Centrus Energy has supplied nuclear fuel and services to utilities since 1998, totaling more than 1,850 reactor-years of fuel by its count. It is working to rebuild large-scale US uranium enrichment at its Piketon, Ohio site, with additional expansion planned in Oak Ridge, Tennessee, and is one of the few companies positioned to produce HALEU domestically, a fuel many next-generation reactor designs depend on.

Sources

Source: Meta’s Prepayment Is Buying Oklo’s Nuclear Fuel for Up to Five Reactors (TIKR.com), an analysis of Oklo’s Meta-backed HALEU contracts with Centrus Energy.

Primary sources: Oklo Form 10-Q, filed November 6, 2026; Centrus Energy Form 8-K, filed November 12, 2026; Oklo, Centrus Secure Fuel Supply for Aurora Powerhouse Deployment in Ohio (Exhibit 99.1 to Centrus 8-K, November 12, 2026); Centrus Energy Form 8-K, filed November 10, 2026; Centrus Energy Appoints Kevin Graney to Board of Directors (Exhibit 99.1 to Centrus 8-K, November 10, 2026); Meta Platforms Form 8-K, filed November 12, 2026.