Oklo’s $35M Take-or-Pay Ties AI Nuclear Fuel Money to Centrus Milestones

Uranium enrichment centrifuge hall in Ohio illustrating Oklo's $35 million HALEU prepayment to Centrus Energy

TL;DR · 30-second read

The Short Version

Oklo, a company designing a new kind of nuclear power plant, will pay uranium supplier Centrus Energy $35 million in advance for fuel that won’t start arriving until 2029.

The money helps Centrus build the Ohio plant that makes this specially concentrated uranium. Oklo also promised to pay for set amounts of fuel from 2029 to 2031, even if it doesn’t use them.

The catch: one payment comes only if Centrus hits an agreed goal, and Oklo can pull out if the plant falls behind. Facebook owner Meta has agreed to pay Oklo ahead for future power, so the fuel gets paid for years before any electricity flows.

Oklo Inc. will make two prepayments totaling $35 million to Centrus Energy for high-assay low-enriched uranium (HALEU) enrichment services, according to a Form 8-K that Oklo filed with the SEC on November 17, 2026. An 8-K is the report a public company files when a material event occurs. The underlying HALEU Supply Agreement was signed on November 11 by Oklo Power SODI LLC, a wholly owned Oklo subsidiary. Under it, Oklo commits, subject to certain conditions, to buy specified quantities of enrichment services for delivery from 2029 through 2031 on a take-or-pay basis.

One prepayment is due on a specified date. The other is due when Centrus achieves a specified commercial milestone. Both are credited against future purchases. The contract runs until the later of December 31, 2039, and completion of both parties’ obligations. Oklo’s filing says the agreement is separate from a September 30 HALEU contract tied to Oklo’s January 2026 deal with Meta Platforms. It follows a November 12 joint announcement in which the two companies said they had signed multiple definitive, multi-year fuel contracts but did not give the size of the prepayments.

Executive Summary

The November 17 8-K puts the first hard number on what Oklo and Centrus had described a week earlier only as “meaningful prepayments.” Oklo is developing Aurora fast-fission powerhouses and has a planned 1.2-gigawatt campus in Ohio supported by a Meta prepayment. It is now committing $35 million in cash toward an enrichment plant that has to be built before its fuel can exist. In its own words, the prepayments are “intended to support the construction and development of Centrus’s commercial HALEU enrichment capacity at Piketon, Ohio.”

HALEU is uranium enriched to between 5% and 20% uranium-235, the isotope that sustains a fission reaction. Many advanced reactor designs, including Aurora, are built to use it. The deal’s structure matters as much as its size. Oklo is acting partly as a fuel customer and partly as a construction financier, while keeping the right to suspend unpaid installments or terminate the contract if Centrus misses development milestones.

For technology companies turning to nuclear power for new electricity, the deal shows where the money actually starts moving. According to the November 12 announcement, Meta’s prepayment to Oklo supports Oklo’s Ohio fuel procurement, and Oklo’s prepayments support Centrus’s build-out. All of this happens years before the first fuel deliveries in 2029.

The $35 Million Is Gated by Centrus’s Own Build Milestones

The 8-K’s mechanics turn an ordinary supply contract into something closer to staged construction finance. Only one of the two prepayments is tied to the calendar. The other becomes payable only when Centrus reaches a specified commercial milestone. Oklo also holds rights to suspend any prepayment not yet due, or to terminate the agreement, in specified circumstances relating to Centrus’s development milestones. The contract further includes replacement and delivery-delay provisions. Their names point to remedies if fuel must be sourced elsewhere or arrives late, but the detailed terms sit in an exhibit Oklo filed with confidential portions omitted.

As a result, a meaningful part of Oklo’s cash is conditional on Centrus’s progress at Piketon rather than paid on signature. That matters to three parties. Centrus gets a committed buyer and partial funding, but not unconditional money. Oklo limits its exposure if the enrichment build slips. Meta’s planned Ohio power depends on Oklo having fuel, so it now sees fuel-supply risk managed through contract milestones, though not removed.

Both payments are credited against future purchases. In economic terms they are an advance on fuel Oklo intends to buy, not a grant or an equity stake. The filing calls them “a portion of the amounts payable,” so the $35 million is the visible part of a contract whose total value, volumes and prices Oklo has kept confidential.

Upstream First: The Fuel Bill Arrives Before the Power

Enrichment means spinning uranium in centrifuges to raise its share of uranium-235. New capacity is capital-intensive, and suppliers want committed buyers before they build it. Centrus CEO Amir Vexler said Oklo’s prepayments “add to the others we have previously received” and “will help fund our build out.” Centrus also said it has secured $5.4 billion in customer contracts and commitments to buy LEU and HALEU from its new capacity. Oklo’s prepayment is a modest slice of that total, but it is cash rather than only a signed commitment.

The Ohio funding chain is unusually explicit. The November 12 announcement says Meta’s prepayment for future Oklo power supports Oklo’s HALEU purchase and secures fuel for the first phase of the planned 1.2 GW Ohio campus. Oklo then prepays Centrus to help build the capacity that will produce that fuel. Money moves from the electricity buyer to the reactor developer to the fuel producer, and each step comes years ahead of the product it pays for. Oklo’s 8-K notes that the new $35 million agreement is distinct from the September 30 Meta-linked contract, which means Oklo is now committing fuel money on more than one contract.

The supply need goes beyond Ohio. Oklo’s first Aurora powerhouse in Idaho relies on an allocation of recovered EBR-II fuel from Idaho National Laboratory. The companies said the Centrus contracts cover the Ohio campus, future Aurora projects and later refueling of the Idaho unit. Put differently, every Oklo reactor after the first depends on enrichment capacity that is still being built.

Take-or-Pay Moves Demand Risk Onto the Reactor Developer

Take-or-pay means Oklo pays for its contracted volumes whether or not it takes delivery. For Centrus, that commitment helps justify building capacity. For Oklo, it creates a fuel obligation for 2029-2031 deliveries before the Ohio powerhouses it is meant to supply have been built.

Two features soften the obligation. The commitment is “subject to certain conditions,” and the suspension and termination rights protect Oklo if Centrus falls behind. As described, however, those protections are tied to the supplier’s milestones. Oklo has not said publicly how the contract treats a delay on its own side, such as a slower licensing or construction schedule for the Ohio units. The contract runs to the later of end-2039 and completion of obligations, which signals that both sides expect a relationship well beyond the three-year delivery window.

Centrus’s Execution Is Now Oklo’s Risk Too

Centrus says it has completed and begun shipping its first new centrifuge and has assembled a complete, “unobligated” supply chain. In the nuclear sector, unobligated means free of foreign-origin restrictions, so the output can serve national-security customers as well as commercial ones. On November 10, Centrus added Kevin Graney, a former president of General Dynamics Electric Boat, to its board. Chairman Mikel Williams cited Graney’s experience guiding production capacity expansions.

Centrus’s own forward-looking statements list the variables that now bear on Oklo’s money: government funding levels for HALEU, its lease on the Piketon facility, and its ability to carry out planned expansions in Piketon and in Oak Ridge, Tennessee. By linking part of its prepayment to Centrus milestones, Oklo has made its fuel timeline and its cash outflow depend on the same execution risks.

Background

Oklo is developing Aurora fast-fission powerhouses, as well as nuclear fuel recycling and a domestic supply chain for critical isotopes. The company says it was the first to receive a U.S. Department of Energy site use permit for a commercial advanced fission plant, was awarded fuel from Idaho National Laboratory, and submitted the first custom combined license application for an advanced reactor to the Nuclear Regulatory Commission. In January 2026 it signed an agreement with Meta Platforms that links Meta’s prepayment for future power with progress on Oklo’s projects, including a planned 1.2-gigawatt campus in Ohio.

Centrus Energy has supplied nuclear fuel and services to utilities since 1998 and says it has delivered more than 1,850 reactor-years of fuel. It is building commercial uranium enrichment capacity at its American Centrifuge Plant in Piketon, Ohio, aiming at both LEU, the conventional reactor fuel, and HALEU, the higher-enrichment fuel many advanced reactors need. Centrus has positioned this effort as part of restoring large-scale U.S. uranium enrichment capability.

Sources

Source: Oklo will prepay Centrus $35 million for HALEU enrichment under a take-or-pay deal, filing shows, a report on Oklo’s November 17 Form 8-K disclosing the size and structure of its HALEU prepayments to Centrus.

Primary sources: Oklo Inc. Form 8-K, filed November 17, 2026 (Item 1.01, HALEU Supply Agreement); Centrus Energy Form 8-K, filed November 12, 2026; Oklo and Centrus press release, “Oklo, Centrus Secure Fuel Supply for Aurora Powerhouse Deployment in Ohio,” November 12, 2026 (Centrus 8-K Exhibit 99.1); Centrus Energy Form 8-K, filed November 10, 2026 (board appointment); Centrus Energy press release, “Centrus Energy Appoints Kevin Graney to Board of Directors,” November 10, 2026 (Exhibit 99.1).