TeraWulf’s 1 GW Data Campus Now Hinges on Kentucky Approving a 760 MW Gas Plant

Natural gas power plant beside high-voltage substation in eastern Kentucky, illustrating Kentucky Power's 760 MW plan for TeraWulf Muskie

TL;DR · 30-second read

The Short Version

  • TeraWulf, a company that builds data centers (warehouses full of computers), plans a campus in eastern Kentucky that could eventually use more electricity than a brand-new power plant produces.
  • The local utility, Kentucky Power, has asked state regulators for permission to build a new natural gas power plant and a large electrical hub to serve it.
  • In return, TeraWulf would pay $100 million toward local households’ winter electric bills over ten years, starting in 2029.
  • Nothing is final. Regulators may not rule until mid-2027, and the campus cannot run without that answer.

On November 13, 2026, Kentucky Power, an operating company of American Electric Power (AEP), asked the Kentucky Public Service Commission (PSC) to approve a new 760-megawatt (MW) combined-cycle natural gas plant next to its Big Sandy unit in Louisa and a new transmission substation in the EastPark Industrial Park area. Both are intended to serve TeraWulf’s planned Muskie Data Campus in Grayson, Kentucky, which is expected to reach up to 1 gigawatt (GW) of contracted electric demand in phases by 2029.

Kentucky Power says the project would give its customers more than $500 million in fixed-cost rate offsets over the life of the agreement and $100 million in winter bill credits for residential customers. TeraWulf would fund those credits starting in 2029 and continuing over the first 10 years of the contract. The plant and substation each need separate approvals, and decisions could come as early as mid-2027.

Executive Summary

Kentucky Power’s filing is the regulatory follow-through on an amended agreement announced in October. In that agreement, according to TeraWulf’s third-quarter earnings release filed with an 8-K on November 6, Muskie’s contracted power doubled from 500 MW to 1,000 MW, subject to PSC approval. The new filing spells out what the utility needs to build to deliver that power: a 760 MW gas plant and a new substation, each requiring its own state certificate.

The filing matters because it shows that the gating items for a gigawatt-scale data campus are new generation and a favorable regulatory ruling. A signed electric service agreement does not settle either one. It also puts on the record how Kentucky Power intends to keep its roughly 162,000 existing customers from paying for that buildout. TeraWulf would pay all applicable service charges and the estimated financing costs of the new plant. Under the utility’s large-load tariff, TeraWulf would also post financial backing before connecting. Residential customers would receive $100 million in winter credits.

For TeraWulf, Muskie is a different kind of asset from its Justified campus in Hawesville, which already has a 20-year Anthropic lease and a Google credit backstop. At Muskie, the power path is what is being secured first. Its value now rides on the PSC’s schedule.

Why a Signed Gigawatt Still Waits on a Gas Plant

TeraWulf’s November 6 results release described Muskie’s power as expanded to 1,000 MW through amended electric service and transmission agreements with Kentucky Power. The same sentence said the expansion is subject to approval by the Kentucky PSC. Chief executive Paul Prager said Muskie “gives us a contracted path to a gigawatt.” Kentucky Power’s November 13 filing shows what that path physically requires. The utility proposes a 760 MW combined-cycle gas plant at Big Sandy in Louisa; combined-cycle plants pair gas turbines with a steam turbine driven by their waste heat. It also proposes a new transmission substation in the EastPark area, the high-voltage yard that receives bulk power and steps it down for a large customer. Kentucky Power says it needs both “to reliably serve that demand.”

Each facility requires its own Certificate of Public Convenience and Necessity (CPCN), the commission’s formal finding that a new utility facility is needed. Kentucky Power says decisions could come as early as mid-2027, while Muskie’s demand is expected in phases by 2029, “subject to regulatory approval and construction schedules.” That sequence is the operational crux. The earliest possible ruling arrives roughly 18 to 30 months before the 2029 target, depending on where in 2029 the phases land. Any slippage in review pushes back the start of construction on a plant and substation that have not yet been approved.

The numbers also do not line up one-for-one. A 760 MW plant is smaller than 1 GW of contracted demand. The new plant is clearly the centerpiece of the supply plan, but it is not presented as the entire answer. Muskie is one case and should not be read as an industry-wide rule. Still, it shows plainly that at gigawatt scale, a utility contract functions as a reservation. That reservation becomes deliverable power only once new generation is approved, financed and built.

Growth Pays for Growth, on Paper and Pending Review

Kentucky Power frames the filing around protecting existing customers. It signed the White House Ratepayer Protection Pledge, which it describes as a commitment that “growth should pay for growth.” Its large-load tariff requires data centers to provide financial backing for the cost of serving them before they connect. On top of all applicable service charges, TeraWulf has agreed to pay the estimated financing costs of building the Big Sandy plant. Kentucky Power president Cindy Wiseman said the utility wants “our customers and communities to share directly in the benefits when new investment comes to the region.”

The concrete benefit is the $100 million in winter credits, which averages $10 million a year across the 10-year window beginning in 2029. The larger figure, more than $500 million in fixed-cost rate offsets, depends on assumptions the release does not show. Those offsets are, broadly, the share of the utility’s fixed system costs that the new customer’s payments are expected to cover. The figure is stated “over the life of the agreement,” and that life is not specified. Both benefits depend on PSC approval and, practically, on Muskie’s load actually arriving.

That is where the commission’s review will concentrate. When a single customer’s demand triggers a new power plant, the protections that matter most only become relevant if the load comes in late, smaller than planned, or not at all. The relevant details are the size and form of the tariff’s financial backing and how plant costs would be recovered in that scenario. The structure Kentucky Power describes points in the right direction. Whether it fully insulates existing customers is what the regulatory record has to establish.

Muskie Is TeraWulf’s Power-First Bet; Justified Is Its Tenant-First One

TeraWulf’s two Kentucky campuses are at different stages. At Justified in Hawesville, a November 4 8-K details a 20-year Anthropic lease for about 401 MW of critical IT capacity, which TeraWulf values at roughly $19 billion. Google agreed to backstop certain of Anthropic’s lease obligations. If Anthropic defaults, Google can pay the rent and assume the lease, or in certain circumstances pay a termination fee and take equity in the project subsidiary. TeraWulf also signed a Fluor construction contract, with deliveries expected from late 2027 through the second quarter of 2028. Muskie, by contrast, appears in TeraWulf’s third-quarter materials as contracted power, with no named tenant.

Securing power before tenants is a deliberate strategy. TeraWulf has reaffirmed a target of contracting 250 to 500 MW of new critical IT capacity a year, and an approved gigawatt at Muskie would be a large reserve to draw on. Critical IT capacity is the power delivered to servers, which is smaller than a site’s total electric demand. TeraWulf has not stated Muskie’s IT figure. The company ended the quarter with about $2.4 billion in cash, cash equivalents and restricted cash. It has expanded its revolving credit facility to $400 million and expects roughly $280 million more from the Abernathy joint venture sale. Its third-quarter adjusted EBITDA, an earnings measure that excludes interest, taxes and non-cash charges, was about negative $12.8 million. Reported net income of $709.9 million came largely from a non-cash change in the fair value of warrants.

The Kentucky Power filing therefore converts Muskie’s most valuable attribute, secured power, into a dated regulatory event. If the PSC approves both certificates on schedule, TeraWulf holds a gigawatt-scale site with a power plant under construction to market to AI and high-performance computing customers. If review stretches out, the 2029 phasing and the timing of the bill credits move with it.

Background

TeraWulf, originally known for bitcoin mining, now describes itself as a vertically integrated owner, developer and operator of power-backed digital infrastructure for high-performance computing and AI. Leasing to computing tenants made up about 83% of its $76.2 million in third-quarter 2026 revenue. It operates the Lake Mariner campus in New York, with 102 MW of critical IT capacity online and 336 MW under construction. It is developing two Kentucky campuses: Justified in Hawesville, leased to Anthropic, and Muskie in Grayson.

Kentucky Power, part of American Electric Power, serves about 162,000 customers across 20 eastern Kentucky counties. It announced its amended agreement with TeraWulf in October 2026. The November 13 filings begin the formal regulatory review of that agreement and of the generation and transmission it requires.

Sources

Source: Kentucky Power Files Plans to Deliver Customer Savings and Advance Kentucky’s Economic Future, Kentucky Power’s November 13, 2026 announcement of its PSC filings for a 760 MW gas plant and substation to serve TeraWulf’s Muskie Data Campus.

Primary sources: TeraWulf Form 10-Q for the quarter ended September 30, 2026 (filed November 6, 2026); TeraWulf Form 8-K (November 6, 2026); TeraWulf Reports Third Quarter 2026 Results (Exhibit 99.1); TeraWulf Q3 2026 Investor Update presentation (Exhibit 99.2); TeraWulf Form 8-K on Justified Google Credit Support Agreements (November 4, 2026); TeraWulf Secures Google Credit Backstop for Project Financing in Support of $19 Billion Anthropic Lease; Executes Definitive Fluor EPC Agreement (Exhibit 99.1).