	<title>Force Majeure &#8211; Jain.com</title>
	<atom:link href="https://www.jain.com/tag/force-majeure/feed" rel="self" type="application/rss+xml" />
	<link>https://www.jain.com/</link>
	<description>Data centers, connectivity, and security — news and analysis</description>
	<lastBuildDate>Sat, 26 Sep 2026 11:15:53 +0000</lastBuildDate>
	<language>en-US</language>
	<sy:updatePeriod>
	hourly	</sy:updatePeriod>
	<sy:updateFrequency>
	1	</sy:updateFrequency>
	

<image>
	<url>https://www.jain.com/assets/img/e2794d1c-jain-com-icon-512-150x150.png</url>
	<title>Force Majeure &#8211; Jain.com</title>
	<link>https://www.jain.com/</link>
	<width>32</width>
	<height>32</height>
</image> 
	<item>
		<title>Oracle&#8217;s 2.4 GW Bloom Reaffirmation Shows On-Site AI Power Trades on Delivery Risk</title>
		<link>https://www.jain.com/bloom-energy-oracle-2-4-gw-fuel-cell-contract-reaffirmed-force-majeure</link>
		
		<dc:creator><![CDATA[Deepak Jain]]></dc:creator>
		<pubDate>Sat, 26 Sep 2026 11:15:53 +0000</pubDate>
				<category><![CDATA[Power Infrastructure]]></category>
		<category><![CDATA[AI data centers]]></category>
		<category><![CDATA[Bloom Energy]]></category>
		<category><![CDATA[Force Majeure]]></category>
		<category><![CDATA[fuel cells]]></category>
		<category><![CDATA[On-Site Power]]></category>
		<category><![CDATA[Oracle]]></category>
		<guid isPermaLink="false">https://www.jain.com/bloom-energy-oracle-2-4-gw-fuel-cell-contract-reaffirmed-force-majeure</guid>

					<description><![CDATA[Bloom Energy shares rose about 8% after Oracle reaffirmed its 2.4 GW fuel cell contract following a force majeure notice. The deal's size never changed, so the rally shows investors price on-site AI power on delivery certainty and on one hyperscale buyer's word.]]></description>
										<content:encoded><![CDATA[<div class="jain-post-grid">
<div class="jain-post-main">
<section class="jain-tldr" aria-label="Plain-English summary">
<p class="jain-tldr-kicker">TL;DR · 30-second read</p>
<h2>The Short Version</h2>
<p>Oracle, one of the giant companies that rents out computing power over the internet, has confirmed it still plans to buy a huge amount of power equipment from a company called Bloom Energy.</p>
<p>The equipment is fuel cells: machines that turn natural gas into electricity on site without burning it. Together they would produce roughly as much power as two large nuclear reactors, to run artificial intelligence computer centers.</p>
<p>A formal warning had said deliveries might be disrupted. When Oracle said the deal was still on, Bloom&#8217;s stock jumped about 8 percent. The deal didn&#8217;t get bigger. Investors were simply relieved it would happen.</p>
</section>
<p>Bloom Energy shares climbed after Oracle reaffirmed its commitment to a 2.4 gigawatt (GW) fuel cell contract that had been put in question by a force majeure notice. A force majeure notice is a formal warning that events outside a party&#8217;s control may delay or prevent it from meeting its obligations. Yahoo Finance put Bloom&#8217;s gain at 8.7%, and 24/7 Wall St. reported a jump of about 8%.</p>
<p>The contract covers on-site fuel cell generation intended to power AI data center capacity. Oracle&#8217;s reaffirmation left the headline size of the commitment unchanged at 2.4 GW.</p>
<h2>Executive Summary</h2>
<p>Oracle has publicly stood by a 2.4 GW fuel cell agreement with Bloom Energy after a force majeure notice raised the possibility that deliveries under the contract could be disrupted. Investors responded by bidding Bloom&#8217;s shares up roughly 8% to 8.7%.</p>
<p>The notable part is what did not change. The contract was 2.4 GW before the notice and 2.4 GW after it. The share move therefore reflects restored confidence that the equipment will actually be delivered and used, not any new demand. That is a useful read on how the market values on-site power for AI. The megawatts on paper matter less than whether the delivery chain behind them holds.</p>
<p>The episode also highlights concentration. A single customer&#8217;s statement about a single contract moved Bloom&#8217;s valuation this much, which suggests investors see this relationship as central to the company&#8217;s outlook. Bloom has not publicly quantified that dependence.</p>
<h2>A Reaffirmation, Not a New Order, Moved the Stock</h2>
<p>Bloom&#8217;s rally did not come from new business. The contracted capacity stayed at 2.4 GW, and no expanded scope was announced. What changed was the perceived probability that the contract would be performed as planned. A move of roughly 8% to 8.7% on that alone is effectively a market price on delivery risk. Before the reaffirmation, investors were discounting the chance that the notice would lead to delays, renegotiation or a smaller commitment. Oracle&#8217;s statement removed much of that discount.</p>
<p>The mechanism runs through the force majeure clause. That clause lets a party suspend or delay its obligations when an event beyond its control intervenes. For on-site generation, performance depends on a long chain: fuel cell modules have to be manufactured, shipped, installed, connected to a gas supply, permitted and commissioned. A notice under that clause signals that at least one link is under strain. For the buyer, the stakes are high, because on-site fuel cells are the power plant for the data center. If the modules arrive late, the computing capacity switches on late.</p>
<p>Three groups feel that directly. Bloom&#8217;s shareholders are exposed because revenue timing depends on delivery. Oracle&#8217;s capacity plans assume the power arrives on schedule. Contractors and lenders have built plans around the same timeline. For on-site AI power, the variable that moves value is delivery certainty, and this episode puts a number on how much.</p>
<h2>Why AI Builders Are Taking Power Into Their Own Hands</h2>
<p>Large AI data centers need enormous, steady amounts of electricity. Connecting that much new demand to the utility grid often means joining an interconnection queue, the line of projects waiting for grid operators to study and approve new connections, and that wait can stretch for years. On-site generation offers a way around it. Fuel cells can be installed next to the data center and added in modules as capacity grows.</p>
<p>That speed comes with a trade-off. An operator that generates its own power exchanges dependence on a regulated utility for dependence on a vendor contract. That means exposure to the manufacturer&#8217;s factory output, to natural gas pipeline availability and to local air permits. Fuel cells avoid combustion, but they still emit carbon dioxide when running on natural gas, so permitting and emissions questions do not disappear.</p>
<p>Scale sharpens the risk. A gigawatt is 1,000 megawatts, and 2.4 GW is roughly the output of two to three large nuclear reactors. At that size, on-site generation is no longer backup power. It is the primary supply for the campus, so any disruption to it matters.</p>
<h2>One Buyer, Outsized Weight</h2>
<p>The size of the market&#8217;s reaction suggests investors treat the Oracle contract as central to Bloom&#8217;s outlook. Bloom has not said what share of its backlog or expected revenue the contract represents. Concentration of this kind cuts both ways. An anchor customer from the hyperscale tier (the handful of companies running cloud platforms at global scale) validates the technology at a scale few buyers could offer, and it can justify factory expansion. The same concentration means one counterparty&#8217;s decisions on site priorities, schedules or procurement flow directly into Bloom&#8217;s revenue timing.</p>
<p>In fairness to both companies, Oracle&#8217;s reaffirmation is a meaningful signal. A buyer looking to exit or reprice a deal could have used a force majeure notice as leverage, and Oracle chose to stand by the commitment publicly. Still, a public reaffirmation is not the same as disclosed terms. It is not known whether delivery schedules, pricing or remedies were adjusted along the way.</p>
<h2>What Buyers and Financiers Should Take From It</h2>
<p>For data center developers, the practical lesson is in the contract drafting. That includes how force majeure is defined, what remedies apply if delivery slips, whether deliveries are staged against milestones, and what backup supply exists if a vendor cannot perform. These terms carry weight well beyond boilerplate when on-site generation is the campus&#8217;s main power source.</p>
<p>Lenders and equity investors underwriting AI campuses powered on site will likely want more visibility into the vendor&#8217;s manufacturing throughput and the fuel supply behind each project. This episode shows the market is already pricing that risk. Better disclosure is how the discount narrows.</p>
<h2>Background</h2>
<p>Bloom Energy builds solid oxide fuel cells, modular systems that convert natural gas or other fuels into electricity through an electrochemical reaction rather than combustion. The company has positioned its systems as a fast way for data center operators to secure large blocks of power without waiting for grid upgrades, a pitch that has gained traction as AI workloads push electricity demand well beyond what many local grids can supply quickly.</p>
<p>Oracle runs Oracle Cloud Infrastructure and has become one of the most aggressive builders of AI computing capacity. Its proxy statement filed with the SEC on September 25 lists Clayton M. Magouyrk and Michael D. Sicilia, alongside Safra A. Catz, as principal executive officers for the fiscal year ended May 31, 2026. That is the leadership team now responsible for Oracle&#8217;s large power commitments, including the 2.4 GW Bloom contract.</p>
<section class="jain-sources" aria-label="Sources">
<h2>Sources</h2>
<p>Source: <a href="https://news.google.com/rss/articles/CBMikgFBVV95cUxPZ3JIV1BUZGxFc3g5UTdCYjJ0azg1RVFSSkdNOXdKNVl4c1FLRVR4RWpEMk01eXU1SUotVlpRTXc5TkRFS1FIY3FjUzRDbGh2MEhhSG0zTTlyUXJpRnd2c3FQQWZxZ3RRRmRlWHVRX0dKa0Y0bl9ITXRlXzl2TW9LN1RyOU5feHJ6c0lDck5BdVZ6Zw?oc=5">Bloom Energy (BE) Is Up 8.7% After Oracle Reaffirms 2.4 GW AI Fuel Cell Deal Commitment – Has The Bull Case Changed?</a> (Yahoo Finance) and <a href="https://news.google.com/rss/articles/CBMi0wFBVV95cUxObE1xYlkwRHpESU9ELUlqbllKYzNHTG1oVTZEdzlkUGVVMmotQnhhaHNtT0VhaUFITVZFOGEwQUJ5XzZzQl9yNXd6VlNaNDUtWnFBNjlneUlkcW5EV29MdVZ6TE5sWkFRYUw3c3AzQjRMVXo0dTZDRmdRZXFGcDN5SERFVTVIS2s5cFFIQVMyR3JKZGsybmNqWGNiSzNxY2JSUjVOek1UNmQxUmlYdXJLY0tHN1lMUmF0SDJnZ3VnZlJsMF9hTVpYV0pGV2ljanlTTXJr?oc=5">Bloom Energy Jumps 8% as Oracle Reaffirms 2.4 GW Fuel Cell Contract After Force Majeure Notice</a> (24/7 Wall St.): coverage of Bloom Energy&#8217;s share gain after Oracle reaffirmed its 2.4 GW fuel cell contract.</p>
<p>Primary sources: <a href="https://www.sec.gov/Archives/edgar/data/1341439/000119312526402816/orcl-20260925.htm">Oracle Corporation, Schedule 14A definitive proxy statement (DEF 14A), filed with the SEC on September 25, 2026</a>.</p>
</section>
</div>
<aside class="jain-rail">
<section class="jain-gaps" aria-label="What the release does not say">
<p class="jain-gaps-kicker">⚠ What They Aren’t Saying</p>
<h2>What the Release Doesn&#8217;t Say</h2>
<ul>
<li><strong>The notice itself:</strong> Neither company has publicly identified which party issued the force majeure notice or what event it cited, such as a supply, manufacturing, fuel or permitting issue.</li>
<li><strong>Terms after reaffirmation:</strong> Oracle and Bloom have not said whether delivery schedules, pricing, penalties or milestones changed as part of the reaffirmation.</li>
<li><strong>Concentration:</strong> Bloom has not disclosed what share of its backlog or expected revenue the 2.4 GW Oracle contract represents.</li>
<li><strong>Deployment details:</strong> The companies have not specified the sites, the natural gas supply arrangements or the status of air permits for the capacity.</li>
<li><strong>Formal disclosure:</strong> As of this writing, Bloom has not filed a current report (Form 8-K) with the SEC describing the notice or the reaffirmation.</li>
</ul>
</section>
<section class="jain-faq">
<h2>Frequently Asked Questions</h2>
<h3>What did Oracle reaffirm?</h3>
<p>Oracle reaffirmed its commitment to a 2.4 gigawatt fuel cell contract with Bloom Energy after a force majeure notice raised the possibility that deliveries under the agreement could be disrupted.</p>
<h3>What is a force majeure notice?</h3>
<p>It is a formal notice under a contract clause that lets a party delay or suspend its obligations when an event outside its control, such as a supply disruption or natural disaster, prevents it from performing.</p>
<h3>Who issued the force majeure notice and why?</h3>
<p>Neither Oracle nor Bloom Energy has publicly identified which party issued the notice or what event it cited. That is one of the main open questions about the episode.</p>
<h3>How much did Bloom Energy&#x27;s stock move?</h3>
<p>Yahoo Finance reported that Bloom Energy shares were up 8.7% after Oracle&#8217;s reaffirmation, while 24/7 Wall St. reported a jump of about 8%.</p>
<h3>How big is 2.4 gigawatts?</h3>
<p>A gigawatt is 1,000 megawatts. At 2.4 GW, the contract is roughly comparable to the output of two to three large nuclear reactors, which is enough to serve as the primary power source for very large AI data center capacity.</p>
<h3>What is a Bloom Energy fuel cell?</h3>
<p>Bloom makes solid oxide fuel cells, which generate electricity through an electrochemical reaction rather than combustion. They typically run on natural gas and can be installed on site as modular units.</p>
<h3>Why do AI data centers want on-site power?</h3>
<p>Connecting large new loads to the utility grid can involve multi-year waits in interconnection queues. On-site generation lets operators bring capacity online sooner and scale it in modules as demand grows.</p>
<h3>Why did a reaffirmation move the stock if the deal didn&#x27;t grow?</h3>
<p>The notice raised doubt about whether the contract would be performed as planned. Oracle&#8217;s reaffirmation reduced that doubt, so the share move reflects lower perceived delivery risk rather than new demand.</p>
<h3>Did the contract terms change?</h3>
<p>The headline capacity remained 2.4 GW. The companies have not disclosed whether delivery schedules, pricing, penalties or milestones were adjusted as part of the reaffirmation.</p>
<h3>How dependent is Bloom Energy on Oracle?</h3>
<p>Bloom has not disclosed what share of its backlog the Oracle contract represents. The size of the stock reaction suggests investors view the contract as highly material to the company&#8217;s outlook.</p>
<h3>What are the risks of relying on fuel cells for data center power?</h3>
<p>Operators depend on the vendor&#8217;s manufacturing output, natural gas supply, local air permits and installation timelines. When on-site power is the primary supply, a delay anywhere in that chain delays the data center.</p>
<h3>Has Bloom Energy filed anything with the SEC about this?</h3>
<p>As of this writing, Bloom has not filed a current report (Form 8-K) with the SEC describing the force majeure notice or Oracle&#8217;s reaffirmation.</p>
<h3>What should data center developers take from this episode?</h3>
<p>Force majeure definitions, delivery milestones, remedies for delay and backup supply plans deserve close attention in on-site power contracts, because these terms determine who bears the risk when delivery slips.</p>
<h3>What should investors watch next?</h3>
<p>Useful signals include any formal disclosure of the notice&#8217;s cause, confirmation of delivery schedules, evidence of units being installed and commissioned, and whether Bloom adds large customers that reduce reliance on a single buyer.</p>
</section>
</aside>
</div>
<p><script type="application/ld+json">{"@context": "https://schema.org", "@graph": [{"@type": "NewsArticle", "headline": "Oracle's 2.4 GW Bloom Reaffirmation Shows On-Site AI Power Trades on Delivery Risk", "description": "Bloom Energy shares rose about 8% after Oracle reaffirmed its 2.4 GW fuel cell contract following a force majeure notice. The deal's size never changed, so the rally shows investors price on-site AI power on delivery certainty and on one hyperscale buyer's word.", "image": ["https://www.jain.com/assets/img/0f89491c-bloom-energy-oracle-2-4-gw-fuel-cell-ai-data-center.webp"], "author": {"@type": "Organization", "name": "jain.com Editorial"}, "datePublished": "2026-09-26T11:15:52.012093+00:00"}, {"@type": "FAQPage", "mainEntity": [{"@type": "Question", "name": "What did Oracle reaffirm?", "acceptedAnswer": {"@type": "Answer", "text": "Oracle reaffirmed its commitment to a 2.4 gigawatt fuel cell contract with Bloom Energy after a force majeure notice raised the possibility that deliveries under the agreement could be disrupted."}}, {"@type": "Question", "name": "What is a force majeure notice?", "acceptedAnswer": {"@type": "Answer", "text": "It is a formal notice under a contract clause that lets a party delay or suspend its obligations when an event outside its control, such as a supply disruption or natural disaster, prevents it from performing."}}, {"@type": "Question", "name": "Who issued the force majeure notice and why?", "acceptedAnswer": {"@type": "Answer", "text": "Neither Oracle nor Bloom Energy has publicly identified which party issued the notice or what event it cited. That is one of the main open questions about the episode."}}, {"@type": "Question", "name": "How much did Bloom Energy's stock move?", "acceptedAnswer": {"@type": "Answer", "text": "Yahoo Finance reported that Bloom Energy shares were up 8.7% after Oracle's reaffirmation, while 24/7 Wall St. reported a jump of about 8%."}}, {"@type": "Question", "name": "How big is 2.4 gigawatts?", "acceptedAnswer": {"@type": "Answer", "text": "A gigawatt is 1,000 megawatts. At 2.4 GW, the contract is roughly comparable to the output of two to three large nuclear reactors, which is enough to serve as the primary power source for very large AI data center capacity."}}, {"@type": "Question", "name": "What is a Bloom Energy fuel cell?", "acceptedAnswer": {"@type": "Answer", "text": "Bloom makes solid oxide fuel cells, which generate electricity through an electrochemical reaction rather than combustion. They typically run on natural gas and can be installed on site as modular units."}}, {"@type": "Question", "name": "Why do AI data centers want on-site power?", "acceptedAnswer": {"@type": "Answer", "text": "Connecting large new loads to the utility grid can involve multi-year waits in interconnection queues. On-site generation lets operators bring capacity online sooner and scale it in modules as demand grows."}}, {"@type": "Question", "name": "Why did a reaffirmation move the stock if the deal didn't grow?", "acceptedAnswer": {"@type": "Answer", "text": "The notice raised doubt about whether the contract would be performed as planned. Oracle's reaffirmation reduced that doubt, so the share move reflects lower perceived delivery risk rather than new demand."}}, {"@type": "Question", "name": "Did the contract terms change?", "acceptedAnswer": {"@type": "Answer", "text": "The headline capacity remained 2.4 GW. The companies have not disclosed whether delivery schedules, pricing, penalties or milestones were adjusted as part of the reaffirmation."}}, {"@type": "Question", "name": "How dependent is Bloom Energy on Oracle?", "acceptedAnswer": {"@type": "Answer", "text": "Bloom has not disclosed what share of its backlog the Oracle contract represents. The size of the stock reaction suggests investors view the contract as highly material to the company's outlook."}}, {"@type": "Question", "name": "What are the risks of relying on fuel cells for data center power?", "acceptedAnswer": {"@type": "Answer", "text": "Operators depend on the vendor's manufacturing output, natural gas supply, local air permits and installation timelines. When on-site power is the primary supply, a delay anywhere in that chain delays the data center."}}, {"@type": "Question", "name": "Has Bloom Energy filed anything with the SEC about this?", "acceptedAnswer": {"@type": "Answer", "text": "As of this writing, Bloom has not filed a current report (Form 8-K) with the SEC describing the force majeure notice or Oracle's reaffirmation."}}, {"@type": "Question", "name": "What should data center developers take from this episode?", "acceptedAnswer": {"@type": "Answer", "text": "Force majeure definitions, delivery milestones, remedies for delay and backup supply plans deserve close attention in on-site power contracts, because these terms determine who bears the risk when delivery slips."}}, {"@type": "Question", "name": "What should investors watch next?", "acceptedAnswer": {"@type": "Answer", "text": "Useful signals include any formal disclosure of the notice's cause, confirmation of delivery schedules, evidence of units being installed and commissioned, and whether Bloom adds large customers that reduce reliance on a single buyer."}}]}]}</script></p>
]]></content:encoded>
					
		
		
			</item>
		<item>
		<title>Oracle&#8217;s Stargate Notice: A 2.45 GW AI Campus Runs on a Gas-Permit Clock</title>
		<link>https://www.jain.com/oracle-force-majeure-notice-project-jupiter-stargate-new-mexico</link>
		
		<dc:creator><![CDATA[Deepak Jain]]></dc:creator>
		<pubDate>Fri, 25 Sep 2026 21:05:57 +0000</pubDate>
				<category><![CDATA[Power Infrastructure]]></category>
		<category><![CDATA[Bloom Energy]]></category>
		<category><![CDATA[Blue Owl Capital]]></category>
		<category><![CDATA[Force Majeure]]></category>
		<category><![CDATA[natural gas]]></category>
		<category><![CDATA[New Mexico]]></category>
		<category><![CDATA[Oracle]]></category>
		<category><![CDATA[Project Jupiter]]></category>
		<category><![CDATA[Stargate]]></category>
		<guid isPermaLink="false">https://www.jain.com/oracle-force-majeure-notice-project-jupiter-stargate-new-mexico</guid>

					<description><![CDATA[Oracle sent a force majeure notice on Project Jupiter, its 2.45-gigawatt Stargate campus in New Mexico, while saying the site remains on schedule. Its fuel cells need gas from a pipeline now delayed to February 2027, and an air permit is pending, so energy permits set the pace to 2028.]]></description>
										<content:encoded><![CDATA[<div class="jain-post-grid">
<div class="jain-post-main">
<section class="jain-tldr" aria-label="Plain-English summary">
<p class="jain-tldr-kicker">TL;DR · 30-second read</p>
<h2>The Short Version</h2>
<p>Oracle, a major technology company, is the main tenant of a giant planned artificial-intelligence computing site in New Mexico called Project Jupiter. It is designed to use about as much electricity as two and a half large nuclear reactors produce.</p>
<p>Oracle has sent the site&#8217;s builder a legal notice. The notice lets Oracle hold back payments if the site isn&#8217;t ready by 2028 because of events outside its control.</p>
<p>The real issue is power. The site will make its own electricity from natural gas, but the gas pipeline has slipped to 2027 and a key air-pollution permit is still undecided. Oracle says the project is on schedule.</p>
</section>
<p>Oracle has sent a force majeure notice to the developer of Project Jupiter, a 2.45-gigawatt Stargate data center campus in New Mexico, Bloomberg first reported on September 24, as relayed by TechCrunch. Blue Owl Capital said its unit received the notice. According to Bloomberg&#8217;s sources, Oracle is not seeking to exit as the campus&#8217;s main tenant; the notice would instead allow it to delay payments if the facility misses its 2028 target to come online.</p>
<p>Both companies played the move down. “Project Jupiter remains on our planned schedule,” Oracle told CNBC. “We are fully committed to New Mexico and confident in our path forward.” Blue Owl told CNBC that “this notice does not change the financial commitments to this multi-year project.”</p>
<h2>Executive Summary</h2>
<p>A force majeure clause excuses a party from contractual obligations when events outside its control get in the way. Oracle&#8217;s notice cancels nothing. It reserves the right to push back Oracle&#8217;s payments to the developer if Project Jupiter is not ready by 2028, while both Oracle and Blue Owl say no delay is expected and no financial commitment has changed.</p>
<p>The reason the notice matters is the campus&#8217;s power design. Jupiter is meant to generate its own electricity with Bloom Energy fuel cells running on natural gas, and the gas supply around it has already slipped: an Energy Transfer pipeline to the site has been pushed back nearly six months, to February 1, 2027, after regulators repeatedly denied permits. The fuel cells&#8217; air-quality permit is still pending, with a state decision due by November 23.</p>
<p>For one of Stargate&#8217;s flagship sites, the schedule that decides when AI capacity actually arrives now runs through two energy permits rather than through the construction site alone.</p>
<h2>A Notice That Reserves Options, Not an Exit</h2>
<p>Force majeure provisions are standard in energy and commodities contracts, and many contracts require prompt notice of a qualifying event before a party can rely on the clause. A notice can therefore be as much about preserving rights as about predicting a delay. That reading fits both public statements: Oracle says Jupiter is on schedule, and Blue Owl says the financial commitments are unchanged.</p>
<p>Both claims can be true at once, but they do not fully dissolve the tension. A tenant certain of a 2028 delivery has less reason to formally reserve payment relief. The most even-handed interpretation is that the notice works like insurance: it is bought against a risk the buyer does not expect but cannot rule out. The question for everyone else is what that risk is.</p>
<h2>For a 2.45 GW AI Campus, Gas Permits Set the Clock</h2>
<p>Project Jupiter is designed for 2.45 gigawatts, roughly the output of two and a half large nuclear reactors, and it is meant to run on Bloom Energy fuel cells, which turn natural gas into electricity through a chemical reaction rather than by burning it. That makes the campus effectively its own power plant. It also means the facility cannot operate without a steady gas supply, so the pipeline and the fuel-cell permits sit on the critical path, the chain of tasks that sets the earliest possible finish date.</p>
<p>Two links in that chain have already moved. Energy Transfer&#8217;s pipeline to the site is now due February 1, 2027, nearly six months late, after regulators repeatedly denied permits; in August, Bloomberg reported that the route had been changed in response. Separately, New Mexico&#8217;s environment department faces a November 23 deadline to rule on the air-quality permit for the fuel-cell system. Neither is a construction problem that more crews or more capital can speed up. Each is a regulatory decision on its own calendar.</p>
<p>On-site generation is often pitched as a way around years-long waits to connect to the public grid. Jupiter shows the trade-off: it swaps the utility&#8217;s interconnection queue for pipeline routing and air permitting. A February 2027 gas date still leaves room before a 2028 opening, but less than before, and if that margin runs out, the force majeure notice is the mechanism that decides who absorbs the wait.</p>
<h2>Who Carries the Timing Risk</h2>
<p>AI data center developers are taking on steep costs to build capacity ahead of demand from customers like OpenAI. A developer&#8217;s return depends on the tenant&#8217;s payments starting when the building is delivered. A clause letting Oracle defer those payments if 2028 slips shifts the cost of waiting toward the landlord side, here the developer and Blue Owl&#8217;s unit, and toward anyone who financed the project against its expected income.</p>
<p>Blue Owl&#8217;s statement that the notice does not change the financial commitments is accurate on its face: deferring a payment is not cancelling it. But for a project funded on expected cash flow, the timing of that cash matters. Until the parties say how long payments could be deferred and on what terms, outsiders cannot size that exposure.</p>
<h2>A Political Flashpoint With a Deadline Attached</h2>
<p>Jupiter has drawn opposition from residents and environmental groups and has become a political flashpoint ahead of the midterm elections. Oracle has responded with a public outreach campaign in the state aimed at winning over critics, according to Bloomberg. The pending air permit ties that debate directly to the timetable.</p>
<p>Fair questions apply on both sides. Critics&#8217; concerns about gas-fired generation and air quality are exactly what the permit process exists to test, and repeated pipeline permit denials suggest that process has teeth. The companies, for their part, have put confident schedule statements on the record while reserving contractual relief. The November 23 permit decision will be the first hard evidence of which posture the facts support.</p>
<h2>Background</h2>
<p>Stargate is the AI infrastructure initiative that Oracle, OpenAI and SoftBank announced with President Donald Trump early in his second term, with the aim of building very large computing campuses in the United States. Project Jupiter in New Mexico is one of its flagship sites. Oracle is the main tenant; it sent the notice to the project&#8217;s developer, and Blue Owl Capital, an investment firm, said its unit received it.</p>
<p>Jupiter&#8217;s energy plan relies on fuel cells from Bloom Energy running on natural gas, delivered by a pipeline from Energy Transfer, a pipeline operator. Because the campus makes its own electricity rather than drawing primarily from the grid, its gas supply and air-quality permitting are as important to its opening date as the buildings themselves.</p>
<section class="jain-sources" aria-label="Sources">
<h2>Sources</h2>
<p>Source: <a href="https://techcrunch.com/2026/09/24/oracle-sends-force-majeure-notice-on-its-new-mexico-stargate-data-center/">Oracle sends force majeure notice on its New Mexico Stargate data center</a> — TechCrunch, September 24, 2026, reporting Bloomberg&#8217;s account of the notice and statements from Oracle and Blue Owl to CNBC.</p>
<p>Primary sources: <a href="https://www.sec.gov/Archives/edgar/data/1341439/000119312526402816/orcl-20260925.htm">Oracle Corporation, Schedule 14A definitive proxy statement (DEF 14A), filed September 25, 2026</a> — Oracle&#8217;s proxy statement, including executive-compensation disclosures.</p>
</section>
</div>
<aside class="jain-rail">
<section class="jain-gaps" aria-label="What the release does not say">
<p class="jain-gaps-kicker">⚠ What They Aren’t Saying</p>
<h2>What the Release Doesn&#8217;t Say</h2>
<ul>
<li><strong>Triggering events:</strong> Oracle has not said which events its notice cites, including whether the pipeline delay or the pending air permit is named.</li>
<li><strong>Payment terms:</strong> Neither Oracle nor Blue Owl has disclosed how long payments could be deferred, whether any cost accrues during a deferral, or whether the project&#8217;s financing depends on payments starting in 2028.</li>
<li><strong>Contingency power:</strong> The companies have not said whether an alternative gas supply or backup power source exists if the February 1, 2027 pipeline date slips again or the air permit is denied or conditioned.</li>
<li><strong>Phasing:</strong> It is not disclosed how much of the 2.45 gigawatts is scheduled to be online in 2028 versus later phases.</li>
<li><strong>Other sites:</strong> Oracle has not said whether similar notices have been sent on other Stargate campuses.</li>
</ul>
</section>
<section class="jain-faq">
<h2>Frequently Asked Questions</h2>
<h3>What did Oracle send to Project Jupiter&#x27;s developer?</h3>
<p>Oracle sent a force majeure notice on Project Jupiter, its Stargate data center campus in New Mexico. According to Bloomberg&#8217;s sources, the notice would let Oracle delay payments if the facility misses its 2028 target to come online.</p>
<h3>What is a force majeure clause?</h3>
<p>It is a contract provision that excuses a party from its obligations when events outside its control prevent it from performing. Such clauses are common in energy and commodities contracts.</p>
<h3>Is Oracle pulling out of Project Jupiter?</h3>
<p>No. Bloomberg&#8217;s sources said Oracle is not seeking to exit as the campus&#8217;s main tenant. Oracle told CNBC the project remains on its planned schedule and that it is fully committed to New Mexico.</p>
<h3>What did Blue Owl Capital say about the notice?</h3>
<p>Blue Owl, whose unit received the notice, told CNBC that the notice does not change the financial commitments to the multi-year project.</p>
<h3>How big is Project Jupiter?</h3>
<p>The campus is designed to handle 2.45 gigawatts of power, roughly the output of two and a half large nuclear reactors. It is one of the flagship sites of the Stargate AI infrastructure initiative.</p>
<h3>How will Project Jupiter be powered?</h3>
<p>It is meant to run on gas-powered fuel cells from Bloom Energy, which convert natural gas into electricity on site. That makes a reliable gas supply central to the project&#8217;s timeline.</p>
<h3>What happened to the gas pipeline serving the site?</h3>
<p>An Energy Transfer pipeline meant to deliver gas to the campus has been delayed nearly six months, to February 1, 2027, after regulators repeatedly denied permits. Bloomberg reported in August that the route had been changed.</p>
<h3>Which permit is still pending?</h3>
<p>An air-quality permit for the fuel-cell system that would power the campus. New Mexico&#8217;s environment department faces a November 23 deadline to decide on it.</p>
<h3>When is Project Jupiter supposed to come online?</h3>
<p>The target is 2028. The notice matters if that date slips, because it would allow Oracle to delay its payments to the developer.</p>
<h3>Does the notice mean the project will be delayed?</h3>
<p>Not necessarily. Notices like this often preserve contractual rights rather than predict an outcome, and both companies say no delay is expected. The pipeline date and the air permit decision will largely determine whether 2028 holds.</p>
<h3>Why doesn&#x27;t generating power on site remove schedule risk?</h3>
<p>On-site generation avoids waiting to connect to the public grid, but it creates new dependencies. At Jupiter, those are a gas pipeline that needs permits and an air-quality permit for the fuel cells, each on a regulator&#8217;s calendar.</p>
<h3>What is Stargate?</h3>
<p>Stargate is the AI infrastructure initiative that Oracle, OpenAI and SoftBank announced with President Donald Trump early in his second term, focused on building large computing campuses in the United States.</p>
<h3>Why is Project Jupiter politically contentious?</h3>
<p>The campus has drawn opposition from residents and environmental groups and has become a flashpoint ahead of the midterm elections. Oracle has run a public outreach campaign in the state aimed at winning over critics, according to Bloomberg.</p>
<h3>What should investors and buyers watch next?</h3>
<p>The November 23 air-permit decision, progress on the pipeline toward its February 1, 2027 date, and any disclosure of the notice&#8217;s terms, such as how long payments could be deferred and what events it cites.</p>
</section>
</aside>
</div>
<p><script type="application/ld+json">{"@context": "https://schema.org", "@graph": [{"@type": "NewsArticle", "headline": "Oracle's Stargate Notice: A 2.45 GW AI Campus Runs on a Gas-Permit Clock", "description": "Oracle sent a force majeure notice on Project Jupiter, its 2.45-gigawatt Stargate campus in New Mexico, while saying the site remains on schedule. Its fuel cells need gas from a pipeline now delayed to February 2027, and an air permit is pending, so energy permits set the pace to 2028.", "image": ["https://www.jain.com/assets/img/c7499d8a-oracle-force-majeure-project-jupiter-stargate-gas-pipeline.webp"], "author": {"@type": "Organization", "name": "jain.com Editorial"}, "datePublished": "2026-09-25T21:05:54.677710+00:00"}, {"@type": "FAQPage", "mainEntity": [{"@type": "Question", "name": "What did Oracle send to Project Jupiter's developer?", "acceptedAnswer": {"@type": "Answer", "text": "Oracle sent a force majeure notice on Project Jupiter, its Stargate data center campus in New Mexico. According to Bloomberg's sources, the notice would let Oracle delay payments if the facility misses its 2028 target to come online."}}, {"@type": "Question", "name": "What is a force majeure clause?", "acceptedAnswer": {"@type": "Answer", "text": "It is a contract provision that excuses a party from its obligations when events outside its control prevent it from performing. Such clauses are common in energy and commodities contracts."}}, {"@type": "Question", "name": "Is Oracle pulling out of Project Jupiter?", "acceptedAnswer": {"@type": "Answer", "text": "No. Bloomberg's sources said Oracle is not seeking to exit as the campus's main tenant. Oracle told CNBC the project remains on its planned schedule and that it is fully committed to New Mexico."}}, {"@type": "Question", "name": "What did Blue Owl Capital say about the notice?", "acceptedAnswer": {"@type": "Answer", "text": "Blue Owl, whose unit received the notice, told CNBC that the notice does not change the financial commitments to the multi-year project."}}, {"@type": "Question", "name": "How big is Project Jupiter?", "acceptedAnswer": {"@type": "Answer", "text": "The campus is designed to handle 2.45 gigawatts of power, roughly the output of two and a half large nuclear reactors. It is one of the flagship sites of the Stargate AI infrastructure initiative."}}, {"@type": "Question", "name": "How will Project Jupiter be powered?", "acceptedAnswer": {"@type": "Answer", "text": "It is meant to run on gas-powered fuel cells from Bloom Energy, which convert natural gas into electricity on site. That makes a reliable gas supply central to the project's timeline."}}, {"@type": "Question", "name": "What happened to the gas pipeline serving the site?", "acceptedAnswer": {"@type": "Answer", "text": "An Energy Transfer pipeline meant to deliver gas to the campus has been delayed nearly six months, to February 1, 2027, after regulators repeatedly denied permits. Bloomberg reported in August that the route had been changed."}}, {"@type": "Question", "name": "Which permit is still pending?", "acceptedAnswer": {"@type": "Answer", "text": "An air-quality permit for the fuel-cell system that would power the campus. New Mexico's environment department faces a November 23 deadline to decide on it."}}, {"@type": "Question", "name": "When is Project Jupiter supposed to come online?", "acceptedAnswer": {"@type": "Answer", "text": "The target is 2028. The notice matters if that date slips, because it would allow Oracle to delay its payments to the developer."}}, {"@type": "Question", "name": "Does the notice mean the project will be delayed?", "acceptedAnswer": {"@type": "Answer", "text": "Not necessarily. Notices like this often preserve contractual rights rather than predict an outcome, and both companies say no delay is expected. The pipeline date and the air permit decision will largely determine whether 2028 holds."}}, {"@type": "Question", "name": "Why doesn't generating power on site remove schedule risk?", "acceptedAnswer": {"@type": "Answer", "text": "On-site generation avoids waiting to connect to the public grid, but it creates new dependencies. At Jupiter, those are a gas pipeline that needs permits and an air-quality permit for the fuel cells, each on a regulator's calendar."}}, {"@type": "Question", "name": "What is Stargate?", "acceptedAnswer": {"@type": "Answer", "text": "Stargate is the AI infrastructure initiative that Oracle, OpenAI and SoftBank announced with President Donald Trump early in his second term, focused on building large computing campuses in the United States."}}, {"@type": "Question", "name": "Why is Project Jupiter politically contentious?", "acceptedAnswer": {"@type": "Answer", "text": "The campus has drawn opposition from residents and environmental groups and has become a flashpoint ahead of the midterm elections. Oracle has run a public outreach campaign in the state aimed at winning over critics, according to Bloomberg."}}, {"@type": "Question", "name": "What should investors and buyers watch next?", "acceptedAnswer": {"@type": "Answer", "text": "The November 23 air-permit decision, progress on the pipeline toward its February 1, 2027 date, and any disclosure of the notice's terms, such as how long payments could be deferred and what events it cites."}}]}]}</script></p>